![]() Like to get a schedule for "cost forecasting" future resource cost when rates are forecasted to change via agreements. I have been able to set up a template for export/import resource data but only can get the column "Price/Unit1, 2, 3" but not able to get column to reflect "Effective Date" for "Price/Unit1, 2, 3" assigned into future dates/years. ![]() ![]() Like to be able to change/update "Current Project's Resources" data particularly -"Price/Unit1, 2, 3" presently delineated in my schedules for different rates into future years/ "Effective Date"- via an excel export/import template.